BUSINESS CASE
Our Energy Services team started the process of getting Petra Nova back online when operations at the unit were suspended. Energy Services developed and implemented highly comprehensive procedures, checklists, and schedules for long-term layup and preventive maintenance of the shutdown facility equipment.
When asked to restart the unit, Energy Services carefully reviewed the original equipment manufacturer manuals and internal technical guidance to develop a checklist of over 1,500 tasks. Together with the facility staff, and in cooperation with ENEOS Xplora, the team effectively carried out the plan to return all equipment and systems at Petra Nova to operational readiness.
Before: Petra Nova was shut down for just over three years.
After: The plant successfully restarted operations.
Achievement: All systems were tested successfully before returning the facility to service.
ENERGY FACTS
After completing the plan to get Petra Nova back to service, our Energy Services team and ENEOS Xplora achieved the following:
The Petra Nova project is a valuable example of how carbon capture utilization and storage (CCUS) can be used to reduce emissions from fossil fuel-fired power plants. It’s a positive development for CCUS technology and could help pave the way for wider adoption of this important technology that helps to address climate change.